Romania Fuller Center for Housing - Build Days 2, 3 & 4

Jucu de Sus, Romania – 2024. The Fuller Center for Housing of Cluj Romania, partnering with a Romanian charity, Association ACASA, builds housing in Jucu de Sus, a village not far from Cluj-Napoca. I was with a team of 18 volunteers on a weeklong build. Day 2 at the build site started with everyone digging and moving dirt and clay to level off an area behind duplex 2 and 3. Day 3 was more moving of dirt but fewer people doing it. Contractors were on site to pour a foundation for another duplex. Because the hillside was unstable and the water table very high the foundation trench must be excavated and the concrete poured on the same day.
Day 2 - Starting to dig out the hill and level the area behind Duplex 3. In this area the dirt and clay was dry and very hard. Fuller Center work site, Jucu de…
Day 2 - Digging out and levelling the area behind Duplex 2. The dirt and clay in this area was very wet, sticky and heavy. Fuller Center work site, Jucu de Sus,…
Day 2 - This clay had been moved from behind Duplex 2 to the side to form a base for a sidewalk. Fuller Center work site, Jucu de Sus, Romania
Day 2 - Dirt moved to the side of Duplex 3. It will be levelled and packed down after the scaffolding has been removed. Fuller Center work site, Jucu de Sus,…
End of Day 2 - Some progress has been made raising the area directly behind Duplex 3. Fuller Center work site, Jucu de Sus, Romania
End of Day 2 - Behind Duplex 2. Fuller Center work site, Jucu de Sus, Romania
Day 3 - Contractors were on site to construct a foundation for an additional duplex. They used an excavator to dig the foundation trenches. Fuller Center work…
Day 3 - A cement truck with a pump boom. Fuller Center work site, Jucu de Sus, Romania
Day 3 – A contractor pumping the concrete into the trenches. Fuller Center work site, Jucu de Sus, Romania
Day 3 - Continued digging behind Duplex 3. Fuller Center work site, Jucu de Sus, Romania
Day 3 - Pumping the concrete into the trenches. The rebar is added before the concrete sets. Fuller Center work site, Jucu de Sus, Romania
End of Day 3 - A lot of progress has been made digging out the area behind Duplex 2. Fuller Center work site, Jucu de Sus, Romania
Day 4 - The start of a jig to build roof trusses. Fuller Center work site, Jucu de Sus, Romania
Day 4 – Horea (Fuller Romania Engineer) and Jack working on the parging of the new workshop. Fuller Center work site, Jucu de Sus, Romania
Day 4 – Carina and Kristin working at the top of the scaffolding doing parging of the new workshop. Fuller Center work site, Jucu de Sus, Romania
Day 4 - A gravel base and rebar for a concrete pad beside the workshop. (It was completely redone the next day). Fuller Center work site, Jucu de Sus, Romania
A view of the country side from the Fuller Center work site, Jucu de Sus, Romania